June 18, 2004 - first sign of progress
| | | |
| | | |
| | | July 6, 2004 - 3 weeks later - excavator finally came back
|
Until the pool is ready, Ryan has to use his imagination
| One of a couple of big "baked potatos" found during the big dig
| | July 16, 2004 - Steel frame is being built
|
| | | |
July 30, 2004 - Plumbing begins. We are now more than 2 months into the project. Plumbing takes about 3 days.
| | | |
| | | |
| | August 9, 2004 - Gunnite for the pool. Takes 7-8 hours and three truck loads to shoot
| |
| | | |
| | | |