Wellington Dam from Carpark Level Construction of the Wellington Dam began in November 1931 and was completed in less than 2 years.
| Wellington Dam beyond the Trees Granite rock was blasted from the nearby quarry and then crushed into small sizes. This was then carried by conveyor belt to be mixed with sand and cement to make concrete for the dam wall.
| Walking down towards the Dam During construction, the crusher, mixer and air compressors were driven by a large steam engine at the site.
| Surrounding Vegetation and Granite Rock Two giant towers were constructed on each side of the valley. Chutes slung between the towers carried concrete to timber formwork that shaped large sections of the wall.
| Wellington Dam from a lower Level The wall was made up of two straight, 76-metre 'wings' that stretched from each side of the valley, joined by an 80-metre curved section in the middle. By diverting the river through two natural channels, the wall was gradually extended across the granite rock base that formed the river bed.
|
Approaching the Viewing Platform In 1944 the height of the dam wall was raised by a metre, and in 1960 it was raised by another 15 metres.
| Construction Information The wall is 366 metres across and 34 metres high. The dam stores about 186 million kilolitres of water when full.
| Collie River Information The total Collie River Catchment covers about 4000 square kilometres and eventually flows into the Leschenault Estuary near Bunbury. In its natural state the River water was fresh but widespread clearing for farmland caused salinity levels in the water to rise making it unfit for drinking.
| Wellington Dam from Lookout Because of its greater density the saline water forms a saline layer at the bottom of the reservoir. The volume of this saline layer is large (40Gl) and each year in an endeavour to reduce the dam salinity level, the Water Corporation scours the saline slug through a large gate valve at the bottom of the dam and discharges it out to sea.
| Discharge of Saline Slug Scouring usually commences 1 July and continues until late October. This saline water is discharged at the rate of 450,000 tonnes per day.
|
Saline Slug flows to the Sea This scouring process has been undertaken continuously over the past 20 years with a discharge of 20-40Gl annually as waste water to the sea.
| Wellington Dam Currently filled to about 82% of its capacity. Since the salinity level became too high for drinking water, the Wellington Dam is now only used to supply up to 68Gl of irrigation water annually.
| Zoom to Gate Valve at bottom of Wall Saline slug is discharged at the rate of 450,000 tonnes per day.
| Zoom to Saline Slug flowing to Sea The Saline slug is discharged at 20-40Gl annually as waste water to the sea.
| Traffic Bridge crossing discharged Saline Slug
|
Wellington Dam from a Lower Level
| Wellington Dam from another viewing spot
| Roadside Cutting Roadside cutting shows gravel composition of soil beneath the Jarrah forest surrounding the dam.
| Another view of Wellington Dam
| Vegetation surrounding Road below Many species of Wildflowers grow here.
|
Twining Fringe Lily (Thysanotus patersonii)
| Hemigenia species
| One-sided Bottlebrush (Calothamnus)
| Bright Pea Flower
| One-sided Bottlebrush (Calothamnus)
|
Hemigenia species
| Mural of Black Swans etched into Granite Rock
| Old Quarry now a Picnic Area Following the completion of the final stage of the dam wall in 1960, the quarry was developed into a picnic area with barbecues and shelters. The sheer quarry face provides an impressive amphitheatre backdrop.
| The Quarry Information Rock to provide the coarse aggregate for use in making concrete for the dam wall was quarried from a granite outcrop close to the dam construction site.
| Bald Granite Face A project engineer at the time described it as: 'a bald granite face some 40 feet high with practically no overburden'.
|
Sheltered Picnic Area The availability of the granite rock and a sand pit 9 kilometres away made the whole project viable.
| Granite Rock Face The rock face was drilled with jackhammers and then blasted. The rubble was carted to a crusher which reduced the stone to a size between 7 and 8 centimetres.
| Carpark in Old Quarry The first rock crusher proved unreliable and after a succession of breakdowns a 'Jacques Jaw Crusher' was brought over from Harvey. The crushed rock was fed by conveyor belt into a bin where it was mixed with sand and cement, then gravitated by chute directly to the concrete mixer.
| Rock Face now used for Abseiling Large rocks, or 'plums' (bigger than 15cm) were originally fed into the crusher but this contributed to the regular breakdowns. Then engineers decided to source large rocks directly from the excavations for the foundation of the dam wall. The workers manhandled the rocks by wheelbarrow and tipped them into the conctete pouring boxes. It is estimated these 'plums' make up about 10% of the wall.
| Rock Face now used for Abseiling The concrete mix ratio was 1 cement and 3 sand to 6 stone. The front two metres of the wall was made with a stronger mix of 1:2:4. The Quarry was again used to provide rock for the raising of the wall in the late 1950's.
|
Granite Rocks Following the completion of the final stage of the dam wall in 1960, the quarry was developed into a picnic area with barbecues and shelters. The sheer quarry face provides an impressive amphitheatre backdrop.
| Lichen on Granite Rock
| Surrounding Countryside
| Cottonheads (Conostylis)
| Yellow Buttercup (Hibbertia)
|