ImageEvent
Public Gallery>Jack Hunter>Miscellaneous>
Basin Renovation
The crumbling riprap walls of the basin, constructed back in 1985, are being replaced with what is expected to be a more durable structure. Dates of the photos appear immediately under each picture.
Jan-Apr 2016116 Images25059 visitsAlbum by AlbacorePhotos by Various
Enlarge photo 1 Artist Rendering.
An artist's representation of what the finished basin will look like.
Enlarge photo 2 01-12-16 (3)
Ground breaking on 12 January. Note that fencing has previously been removed for unfettered access to the basin.
Enlarge photo 3 01-12-16 (1)
Heat blankets have been laid to keep the ground from freezing during construction.
Enlarge photo 4 01-13-16 (3)
Locating the place to excavate for the placement of the sump pit.
Enlarge photo 5 01-13-16 (6)
The sump pit is a key element of the new basin structure.
Enlarge photo 6 01-19-16 (6)
Exploratory excavation alongside the port side of the aft cradle to determine if the cradle and marine railway structures are integrated.
Enlarge photo 7 01-20-16 (2)
Excavation of the dewatering sump and exploratory location of bed rock to see if any bed rock needs to be removed.
Enlarge photo 8 01-20-16 (5)
A closer view of the sump/explorative excavation.
Enlarge photo 9 01-20-16 (6)
Excavation of the dewatering sump.
Enlarge photo 10 Sump Pit Excavation 1
Location of the sump has been moved from the original position to stay away from the propellers and to be closer to the sewer line that runs thru the park grounds.
Enlarge photo 11 Sump Pit Excavation 2
The sump will be the lowest point in the basin and will receive drainage from inside and outside the basin walls.
Enlarge photo 12 Sump Pit Excavation 3
Measuring the depth of the sump pit to ensure it will be the low point of the basin.
Enlarge photo 13 image001.png
This is a sketch of the prefabricate concrete sump to be installed on the port side aft end of the basin.
Enlarge Microsoft PowerPoint Presentation 14 Dewatering Sump & drainage sketch.pptx
The dewatering sump is a key part of the 'new' basin and it's location is critical for success in removing accumulated water.
Enlarge photo 15 01-20-16 (7)
Toe-Wall blocks waiting for installation.
Enlarge photo 16 01-21-16 (2)
Partially excavated aft side of the aft cradle.
Enlarge photo 17 01-21-16 (3)
The aft port lower control surface is completely exposed for the first time in 26 years.
Enlarge photo 18 01-26-16 (7)
Close up of the partially excavated aft cradle. There is a question about the structural stability of the cradle. Specifically, what lies under the cradle - solid bedrock or a shale-like material.
Enlarge photo 19 01-27-16 (1)
Installation of the de-watering catch basin/sump.
Enlarge photo 20 2016 [01-26] (1)
Measuring the depth of the basin aft of the dewatering sump.
Enlarge photo 21 2016 [01-26] (2)
Ice, mud and crud around the sump.
Enlarge photo 22 2016 [02-02] (3)
Lower starboard fin almost free of rip rap and other debris.
Enlarge photo 23 2016 [02-02] (5)
Looking forward from aft of the lower starboard control fin. Note large amount of rip rap that has slid into the lower portion of the basin.
Enlarge photo 24 2016 [02-02] (2)
Looking forward toward the aft cradle. Note less than solid rock appearing material under the cradle.
Enlarge photo 25 2016 [02-02] (4)
Partial arrangement of toe-wall blocks at the after end of the basin.
Enlarge photo 26 2016 [01-29] (1)
View showing the relative positions of the dewatering sump, port lower fin and the end of basin toe-blocks.
Enlarge photo 27 2016 [02-02] (8)
View looking aft from the after cradle toward the end of the basin.
Enlarge photo 28 2016 [02-10] (1)
Excavation continues along the port side. Some toe-wall blocks are in place.
Enlarge photo 29 2016 [02-10] (2)
Note concrete stabilizing pad behind aft cradle.
Enlarge photo 30 2016 [02-10] (10)
Placement of the toe-wall continues up the port side.
Enlarge photo 31 2016 [02-10] (9)
To enhance drainage, old rip rap and other material is removed in order to achieve the desired downward slope from the remnants of the marine railway tracks to the outside of the basin .
Enlarge photo 32 2016 [02-10] (7)
View looking across the basin from the starboard side shows part of the toe-wall and gravel that will form the basin floor.
Enlarge photo 33 2016 [02-10] (6)
The concrete block under the lower port fin is there as a base from which to measure any shift in the sub/fin. Note how near the after most section of the toe-wall is to the dunce cap on the propeller shaft. The basin floor will be smaller when the project is completed.
Enlarge photo 34 2016 [02-12] (3)
This view shows the temporary support for stability of the lower port stern plane.
Enlarge photo 35 2016 [02-12] (8)
View of part of the toe-wall showing the green colored drainage piping on both sides of the wall.
Enlarge photo 36 2016 [02-12] (10)
Port side toe-wall looking forward.
Enlarge photo 37 2016 [02-15] (4)
These are the discharge pipes from the dewatering sump. The sump has two pumps which can be run separately or together.
Enlarge photo 38 2016 [02-15] (1)
The discharge pipes lead from the sump to the existing storm drain system.
Enlarge photo 39 2016 [02-17] (7)
The truck is part of the vacuum system used to remove sand and gravel from under the hull..
Enlarge photo 40 2016 [02-17] (6)
According to the contractor, the project is 9.3 per cent complete as of this date (2/17) and are confident of finishing on time.