• Public Gallery  • Help  
• Join Now!  • Log In  • Feature Tour
 The Vierregger Family | Home > 
The Pool!! Finally, the Pool!!!
The pool dig started the same day as Ginger went into labor.  We considered ourselves complete 15 months later, August 27, 2005.  Please review these pictures carefully if you ever consider undertaking such a project!

Update: 2014.  A wise man once said a pool is a hole in the ground into which one pours money.  That about sums it up!  We still enjoy the pool but maintenance is never far out of mind.  Check out the latest pics at the end of the album to see why I say that.  Cheers
Date(s): June 17, 2004  Updated 2014. Album by The Vierregger Family. 1 - 274 of 274 Total. 2119 Visits.
  Sign the Guestbook. There are no entries.
Start SlideshowTo order prints and photo-products: 1. Select photos. 2. Click Order. 3. Select products.Select images and click to download to your computer 
Enlarge photo 1
1
June 18, 2004 - first sign of progress

Enlarge photo 2
2

Enlarge photo 3
3

Enlarge photo 4
4

Enlarge photo 5
5

Enlarge photo 6
6

Enlarge photo 7
7

Enlarge photo 8
8

Enlarge photo 9
9

Enlarge photo 10
10

Enlarge photo 11
11

Enlarge photo 12
12
July 6, 2004 - 3 weeks later - excavator finally came back

Enlarge photo 13
13
Until the pool is ready, Ryan has to use his imagination

Enlarge photo 14
14
One of a couple of big "baked potatos" found during the big dig

Enlarge photo 15
15

Enlarge photo 16
16
July 16, 2004 - Steel frame is being built

Enlarge photo 17
17

Enlarge photo 18
18

Enlarge photo 19
19

Enlarge photo 20
20

Enlarge photo 21
21
July 30, 2004 - Plumbing begins.  We are now more than 2 months into the project.  Plumbing takes about 3 days.

Enlarge photo 22
22

Enlarge photo 23
23

Enlarge photo 24
24

Enlarge photo 25
25

Enlarge photo 26
26

Enlarge photo 27
27

Enlarge photo 28
28

Enlarge photo 29
29

Enlarge photo 30
30

Enlarge photo 31
31
August 9, 2004 - Gunnite for the pool.  Takes 7-8 hours and three truck loads to shoot

Enlarge photo 32
32

Enlarge photo 33
33

Enlarge photo 34
34

Enlarge photo 35
35

Enlarge photo 36
36

Enlarge photo 37
37

Enlarge photo 38
38

Enlarge photo 39
39

Enlarge photo 40
40

Enlarge photo 41
41

Enlarge photo 42
42

Enlarge photo 43
43

Enlarge photo 44
44

Enlarge photo 45
45

Enlarge photo 46
46

Enlarge photo 47
47

Enlarge photo 48
48

Enlarge photo 49
49
As if it wasn't enough chaos building a pool, our chocolate lab had 9 puppies at the same time, and we built the temporary fence in the front yard to let them play.  Apparently, we are crazy!

Enlarge photo 50
50

Enlarge photo 51
51

Enlarge photo 52
52

Enlarge photo 53
53

Enlarge photo 54
54

Enlarge photo 55
55

Enlarge photo 56
56

Enlarge photo 57
57

Enlarge photo 58
58

Enlarge photo 59
59

Enlarge photo 60
60

Enlarge photo 61
61

Enlarge photo 62
62

Enlarge photo 63
63
August 18, 2004 - Plumbers are back to complete the plumbing.  Pump area to have 5 pumps, 3 blowers, heater and filter

Enlarge photo 64
64
1300 ft of PVC pipe was used

Enlarge photo 65
65

Enlarge photo 66
66

Enlarge photo 67
67

Enlarge photo 68
68

Enlarge photo 69
69
September 23, 2004 - We are three months in to the project.  The fence is going up.

Enlarge photo 70
70

Enlarge photo 71
71

Enlarge photo 72
72

Enlarge photo 73
73

Enlarge photo 74
74

Enlarge photo 75
75

Enlarge photo 76
76

Enlarge photo 77
77

Enlarge photo 78
78

Enlarge photo 79
79

Enlarge photo 80
80

Enlarge photo 81
81
First tile and coping didn't go so well...

Enlarge photo 82
82
Somehow we ended up with about 2" of mud when it should have been only 1/2"...

Enlarge photo 83
83
The whole thing, tile and coping, was removed to fix it.  This meant more delays...

Enlarge photo 84
84
October 5, 2004 - The next crew did an excellent job

Enlarge photo 85
85
So many cuts to make in 2" stone - and all with a handsaw

Enlarge photo 86
86

Enlarge photo 87
87

Enlarge photo 88
88

Enlarge photo 89
89

Enlarge photo 90
90

Enlarge photo 91
91
Finally with water - and just in time for Christmas.  The landscaping is going to have to wait.

Enlarge photo 92
92
The plaster is "medium" gray with 3m ColorQuartz aggregate.  This tints the water a bit.

Enlarge photo 93
93

Enlarge photo 94
94
The pool wasn't opened until December.  It has to be open for about a month to allow the plaster to cure.  Hope it doesn't get too cold...

Enlarge photo 95
95
Oops, a little plumbing glitch and a big freeze cause a bit of ice to form

Enlarge photo 96
96

Enlarge photo 97
97
It's January, but have cleared the patio and yard for major excavation.  Sinking the patio 2 ft and digging foundation for the pool house.

Enlarge photo 98
98
The shed has been emptied and limits of clearing have been painted

Enlarge photo 99
99
500 sq ft of mesh-reinforced concrete have to be broken up.

Enlarge photo 100
100
A view towards the future poolhouse area.

Enlarge photo 101
101
After the excavation, 9 6x6 deck posts will need to be replaced.  They won't go deep enough once the dirt is excavated 2+ feet.

Enlarge photo 102
102
That pile of dirt on the construction road is actually a solid block of ice.  Had to rent a backhoe to break up and remove the 15 yards of dirt/sand/ice in order to access the back yard.

Enlarge photo 103
103
February 5th - The big dig begins... Moving 75 yards of dirt and concrete.

Enlarge photo 104
104
In this picture the patio has already been broken up and hauled away.  It took 5 workers 2.5 days with 2 jack hammers to break up the concrete, and 1 day to haul out.

Enlarge photo 105
105

Enlarge photo 106
106
Don't start a project like building a pool unless you can live with a mess for months on end...

Enlarge photo 107
107
Because so much dirt has to go, hand-digging was used to get away from the house before the Bobcat starts to dig.

Enlarge photo 108
108
Will have to go down 10" below the existing basement slab to make room for the new patio.  Retaining walls will hold back the walls and steps will lead up to the pool deck.

Enlarge photo 109
109
March 15th - the excavators are back after disappearing for 5 weeks.

Enlarge photo 110
110

Enlarge photo 111
111
The bobcat made the job much easier - but there wasn't much room to move around

Enlarge photo 112
112
Instead of hauling, the dirt was piled beside the pool.  Some will be used to fill the back yard around the pool in preparation for the deck.  The rest will still have to go.

Enlarge photo 113
113
The finished product.  6 weeks after starting to dig, this is the end result.  The posts will all have to be replaced because they don't extend in to the ground anymore.

Enlarge photo 114
114
The new patio will be at basement floor height and stone retaining walls will be constructed.

Enlarge photo 115
115
The post in the foreground was tapped by the bobcat.  Good thing it wasn't load bearing - in fact it's dangling in mid-air!

Enlarge photo 116
116

Enlarge photo 117
117

Enlarge photo 118
118
Some of the dirt that was excavated for the patio - most of this will have to be hauled.

Enlarge photo 119
119
Dirt is fun to a boy.  Ryan is playing king of the hill.  Sorry son, that dirt has to go if you want the pool opened this year!

Enlarge photo 120
120

Enlarge photo 121
121
The manual part of moving the dirt around the back yard isn't as fun as it looks

Enlarge photo 122
122
The extra dirt was used to fill in around the back of the pool where the yard sloped off.

Enlarge photo 123
123

Enlarge photo 124
124
March 19th - ready to have the posts replaced...

Enlarge photo 125
125

Enlarge photo 126
126

Enlarge photo 127
127

Enlarge photo 128
128

Enlarge photo 129
129

Enlarge photo 130
130
March 21st - 4 man crew shows up to replace 9 6x6 deck posts with 12 footers.  This is a big job but the crew is very professional and efficient.

Enlarge photo 131
131
Lead carpenter was impressive.

Enlarge photo 132
132
Supports held up the deck while the posts were replaced.

Enlarge photo 133
133
Measure twice, cut once...

Enlarge photo 134
134
The crew managed to swap out 9 posts in a single day.  And they even showed up when they said they would!

Enlarge photo 135
135
April 11th - Workers show up for the patio and stone walls...

Enlarge photo 136
136

Enlarge photo 137
137
The problem with having a sunken patio is what to do with the water.  We are installing a dry system under the new composite deck boards which will keep the patio dry for the most part.  This worker is digging a 3x3x3 dry well store whatever blows in.

Enlarge photo 138
138

Enlarge photo 139
139
Installing rebar for the stone retaining wall footers

Enlarge photo 140
140
The concrete arrives for the 500sf slab under the flagstone patio

Enlarge photo 141
141
12 yards of concrete (2 trucks) were wheelbarrowed to the patio

Enlarge photo 142
142

Enlarge photo 143
143
Worker is measuring the slope of the patio.  The pad had to be sloped to the dry well so water doesn't stand or puddle

Enlarge photo 144
144

Enlarge photo 145
145
Only a rough finish is required for the pad because it will be covered with flagstone

Enlarge photo 146
146

Enlarge photo 147
147
April 16th - the stone masons are on site

Enlarge photo 148
148
Laying the cornerstone - ah, progress!

Enlarge photo 149
149

Enlarge photo 150
150
Flagstone floor and stone walls to be installed around patio

Enlarge photo 151
151

Enlarge photo 152
152

Enlarge photo 153
153

Enlarge photo 154
154

Enlarge photo 155
155
Floor is still dirty - but there seems to be a pretty good color variation in the flagstone

Enlarge photo 156
156

Enlarge photo 157
157
Stones will enclose the wood deck posts

Enlarge photo 158
158
April 21st, the patio is starting to take shape.  The capstone is a 2in. gauged pool coping flagstone - a bit of an upgrade$$$ but looks like a million bucks

Enlarge photo 159
159
The remaining patio is awaiting a gas inspection before completion.  Cheryl and I decided to have a gas firepit installed since the stonemasons were on site anyway...

Enlarge photo 160
160

Enlarge photo 161
161

Enlarge photo 162
162
The decision to run a new gas line to the patio led to 3.5 days of digging and trenching for the gas line - by the homeowner himself!  The 100ft trench for the gas line ran right through the contractors 4ft pile of gravel, and ultimately through the new patio - fun, fun, fun!

Enlarge photo 163
163
Around the pool equipment...

Enlarge photo 164
164
around the future pool house...

Enlarge photo 165
165
and down to the patio.  That was the relative easy part.  Well not really, but it was easier than sawing through the new slab and footer!

Enlarge photo 166
166
The footer was 2ft thick!  The gas line has to run under the footer.

Enlarge photo 167
167
Try digging out 18" of concrete, gravel and clay with a 3" shovel.  It took a day and a half just for the patio portion of the gas line excavation.  I sure hope it was worth it.

Enlarge photo 168
168
More trenches - the left side is for a stone retaining wall to run along the fence.  The right side is for drain lines.

Enlarge photo 169
169
June 30th, 2005 - Workers are preparing for the pool deck

Enlarge photo 170
170
Doesn't that water look refreshing?

Enlarge photo 171
171
The hole in the ground is for the diving board stand - concrete is 12" thick there

Enlarge photo 172
172

Enlarge photo 173
173
14 workers moved the 19 yards of concrete by hand

Enlarge photo 174
174

Enlarge photo 175
175
It was a hot day but the rain held off

Enlarge photo 176
176

Enlarge photo 177
177
We had timber-framed steps run up the side of the house and filled with the same brushed concrete as the pool deck

Enlarge photo 178
178

Enlarge photo 179
179
After draining and cleaning the pool, Ryan and Ginger wait anxiously for the water to rise...

Enlarge photo 180
180
Success!

Enlarge photo 181
181
The spa is just right!

Enlarge photo 182
182
All the fountains in action - Ginger really seems to like the pool

Enlarge photo 183
183
Showing small fountains - they are adjustable using a valve

Enlarge photo 184
184
"Bubbler" fountains

Enlarge photo 185
185

Enlarge photo 186
186

Enlarge photo 187
187
Getting closer to finished...Cheryl just finished painting and new light fixtures are up

Enlarge photo 188
188

Enlarge photo 189
189

Enlarge photo 190
190

Enlarge photo 191
191

Enlarge photo 192
192
The deck is almost done - notice the black roofing material I installed to keep rain off the patio underneath.  It uses a gutter to send water out to a drain.  This turned out to be a massive, time-consuming, heavy job.  Over 3,000 staples and about 1,800 screws, all of which had to be pre-drilled.  Whew!

Enlarge photo 193
193
Showing part of the finished section of deck

Enlarge photo 194
194
Chairs just waiting for a party!

Enlarge photo 195
195
8/15/2005 - The waterfall crew has arrived.  They are building the support structure for the waterfall, placing 1/2" rebar every 12" to reinforce the concrete shell.

Enlarge photo 196
196

Enlarge photo 197
197
Piping on floor is for drains - the flexible pipe is the 2" waterline that feeds the waterfall.

Enlarge photo 198
198
Formed out and ready to go.

Enlarge photo 199
199

Enlarge photo 200
200
A work in progress - concrete shell supports the boulders that become the waterfall.  In the end the shell won't be visible at all.  5.5 large pallets of boulders were used.

Enlarge photo 201
201
The crew had to wheelbarrow the concrete in due to tight space constraints.  It is 4' thick in places!

Enlarge photo 202
202
The completed waterfall.  It is a bit larger than we expected but it's great for climbing on and jumping off.

Enlarge photo 203
203
Ryan and his friend Mark wasted no time in testing out cannon balls from the new waterfall.

Enlarge photo 204
204

Enlarge photo 205
205

Enlarge photo 206
206
The completed patio with firepit.  The firepit is a natural gas appliance using piped-in gas.  It really makes the patio.

Enlarge photo 207
207
This is an early morning shot with the sun coming in from the east.  The patio has a dry roof system so it provides nice shade during the day.  Ceiling fans help cool things down further.

Enlarge photo 208
208
The patio also features recessed lighting with dimmers and a separate dim-able spotlight over the firepit.  More than 450ft of wire was used to wire the patio electrical sytsem.

Enlarge photo 209
209
Notice the gutter system installed at the front of the patio to drain off the water from the deck above.  The gutter goes to the pool deck which drains out to the woods behind the house.

Enlarge photo 210
210

Enlarge photo 211
211

Enlarge photo 212
212
The yard was destroyed during the construction project.  We hired a landscaping firm to regrade and lay down sod.  We even treated the yard to a "spring cleanup" in August.  Better late than never!

Enlarge photo 213
213

Enlarge photo 214
214

Enlarge photo 215
215

Enlarge photo 216
216

Enlarge photo 217
217
The sod is stressed because it's late August.  Only 15 months since the first shovel hit the dirt and our yard is ours again.

Enlarge photo 218
218

Enlarge photo 219
219

Enlarge photo 220
220
We still have a little grass in the back yard!

Enlarge photo 221
221
The end.  Except for the landscaping, fix the sprinkler system, build a shed, screen off the pump equipment...  A successful project is never finished!

Enlarge photo 222
222
UPDATE - January, 2014.  The pool has been open 8 or 9 years now.  We planted some tall laurel evergreens behind the waterfall in 2005 or 2006, and they grew into what we affectionately called "the green monster".

Enlarge photo 223
223

Enlarge photo 224
224

Enlarge photo 225
225

Enlarge photo 226
226

Enlarge photo 227
227

Enlarge photo 228
228

Enlarge photo 229
229
The reason we are updating the album is because the waterfall is sick.  Notice the gap in the stones?  The entire waterfall is sinking backwards.  We attempted a rehab a couple years ago to compensate for the rearward leaning and to waterproof the front side.  It was an expensive, losing battle.  The hulking beast must go.  The reason?  The jackass who built it didn't put footers under it.  And he disappeared by the time we became aware of the problem.

Enlarge photo 230
230
In the foreground, you can see some of the mitigation work, where the waterfall ledge was redone and elevated in the rear so the water could go downhill into the pool.  Cost to mitigate and waterproof the front of the waterfall where it lifted off the coping - too much, and it still needed more work just for mitigation as it is impossible to fix completely.  Add to that the hassle that no one wants to touch the beast and dislodge those big boulders for fear of liability.

Enlarge photo 231
231
It's winter in these pictures, but just trying to document the final state of the waterfall before it is demolished.  The waterfall will be replaced something, but what?

Enlarge photo 232
232
More green monster shots.

Enlarge photo 233
233

Enlarge photo 234
234
Looks kind of like a big chia pet.  The laurels got out of hand,, but they make a great evergreen screen.

Enlarge photo 235
235
Ah, what is missing in this picture?  Demolition has begun!

Enlarge photo 236
236

Enlarge photo 237
237

Enlarge photo 238
238
Using my trusty sawzall, the green monsters were down and hauled to the front in less than 45 minutes.

Enlarge photo 239
239
The former green monster now looking quite sad while waiting to be hauled away.

Enlarge photo 240
240
No more waterfall chia pet.

Enlarge photo 241
241
Now there is room to work.  In a stroke of luck, a landscape company happened to be driving by as I was hauling the laurels up to the front of the house.  They offered to take the laurels to be shredded and while they were loading them up, I talked the foreman into "making that pile of rocks disappear".  Lol.

Enlarge photo 242
242
The demo crew in action.  They have already removed most of the boulders.

Enlarge photo 243
243
Talk about physical, back-breaking work!  A sledge hammer and a breaker bar were used to dislodge all the stones and dolly them up to the street.

Enlarge photo 244
244
After five hours, this is what remains of the waterfall.  It's just a shell of it's former self, no pun intended.

Enlarge photo 245
245
Not a very attractive feature anymore!

Enlarge photo 246
246
On their way out for the day, the guys said "there is a lot of concrete under there".  Uh huh.  I am supplying them a jack hammer to break up the shell.  That concrete is 3 or 4 feet thick in places!

Enlarge photo 247
247

Enlarge photo 248
248
This is what four guys can do in five hours.  Of course, they have to now lift it twice to get it in the truck!  It hurts my back just to think about it.

Enlarge photo 249
249
Forecast for tomorrow? Snow!  But the guys are hungry and said they would be working anyway.  Goodbye yard.

Enlarge photo 250
250
Day2 - we had some snow and it's 15 degrees. Will it stop progress?

Enlarge photo 251
251
Nope! The hard working crew is back and braving the elements.

Enlarge photo 252
252
End of day 2 and the guys have made some progress knocking down the concrete shell.

Enlarge photo 253
253

Enlarge photo 254
254
Can you imagine attempting this with a sledgehammer?

Enlarge photo 255
255
Day 5 of demo.  The crew missed a couple of days due to the Polar Vortex and below 0 degree weather. It was still less than 10 degrees this morning.  The guys asked for a second jackhammer, thinking they could finish.  These 70lb electric jackhammers are just not made for 2-3ft thick concrete so it is a slow process.  Hindsight being 20/20, I should have rented a trailered compressor and heavy duty air hammers - available up to 90lbs.  Live and learn (and pay out the nose).

Enlarge photo 256
256
It's a mess, but the concrete shell is almost gone and the boulders have been hauled out from the front.  One day left I am told.

Enlarge photo 257
257
End of day 5.  Some final demo and lots of cleanup tomorrow.  Weather permitting!

Enlarge photo 258
258
Day 6 of demolition and we can call it complete.  Now the fun starts.  We have opened up a can of worms and will have to deal with the mortar-covered coping in the spring.  At least we have a blank slate and the hard part has been completed.  My hats off to the crew, they really worked their butts off.  More pictures will be posted as things progress.  Cheers

Enlarge photo 259
259
May 20, 2014 - after spirited debate about what to do with the area where the waterfall once stood, a decision was made to extend the pool deck with a flagstone patio inlay.

We considered making this a grill area or an outdoor fireplace.  Too little room and too much hassle to get gas back there, so a new patio it will be.


Enlarge photo 260
260
A deep footer was dug to make sure this patio doesn't sink like the waterfall did.

Enlarge photo 261
261
Everything had to moved by hand.

Enlarge photo 262
262
End of day 1 and the slab is done.

Enlarge photo 263
263
Day 2 - Have to knock out the old coping stones that were ruined by the waterfall.

Enlarge photo 264
264
These stones will have to be replaced and matched as closely as possible. The pool coping actually has a blue-green tint to it and that has proven impossible to find.  Attempting to fill in and replace stone after 10 years means nothing is perfect but hopefully everything will blend.

Getting the old stones out and starting cuts on the new stones consumed day 2.


Enlarge photo 265
265
Day 3 - Cutting and fitting the coping stones is a slow, painstaking process.  The entire perimeter of the new deck area was redone.  Can you see where the old coping stops and the new begins?  It's a pretty good match and the stones still need to be cleaned up.

Enlarge photo 266
266
The new coping is on the left, 8 year old coping is on the right.  This area is adjacent to the rear bar area and should make a nice planting bed for some annual color.

Enlarge photo 267
267
View from the rear bar looking at the new planting bed and pool deck.

Enlarge photo 268
268
The area inside the coping will be filled with irregular flagstone.  There was no way to match the poured concrete deck so we decided to make the area look intentionally different.  We have other flagstone nearby so the theme should carry over.

Enlarge photo 269
269
View from the opposite side of the yard.  The rear bar is in the top left of the picture.  We left 18" on the back side of the pool deck extension to put some narrow evergreens as a fence screen.

Enlarge photo 270
270
Another view from the left side of the yard.

Enlarge photo 271
271
Looking from the deck.

Enlarge photo 272
272
Day 4 - more help arrives to assist with the flagstone installation.  We really like the colors in their stone selection.  It has been a long day to get the jigsaw puzzle figured out.

Enlarge photo 273
273
We had an image in our heads when we decided on a flagstone pool deck "insert" - but it is looking even better than we had envisioned.

Enlarge photo 274
274
These guys are artists with a hammer instead of a brush!

 
 Select All.  
 
Album Properties. Email Album. Send Invitation. Add to Website. Share URL