 1 Almost ready for the 1 piece center section. They estimate the time from when the center section leaves Crown Point Beach to in place will be 19 hours
|  2 Ole Yeller just dont blend in ha ha
|  3 1 of the 2 ferry boats moving traffic while the bridge is built. They run constantly 24/7. During the winter they ran back and forth even empty to keep the broken channel from freezing.
|
 4
|  5 Look righ in front of the crane mid span on the distant shore. The arch you see is the center section. By water its roughly 5 miles from the bridge to crown point beach where they built the center span.
|  6
|
 7
|  8
|  9
|
 10 1/2 of the center span is already up on barges. I guess its going to be moved and lifted soon.
|  11
|  12 Temporary ferry landing on the New York side.
|
 13 Original Bridge
|  14 Ka-Boom, no more original bridge. Blown up December 28 2009
|  15
|
 16
|  17
|  18
|
 19
|  20
|  21
|
 22
|  23
| |