• Public Gallery  • Help  
• Join Now!  • Log In  • Feature Tour
 Public Gallery | Home > Kevin Foust > Miscellaneous > 
Wood Cart
Here's an album on how I rebuilt my little woodcart to stand up to the weight it hauls. Put about a 1/4 of a cord on it at a time  so it can be around 1000 lbs.
Album by Kevin Foust. 1 - 24 of 48 Total. 3295 Visits.
Start SlideshowTo order prints and photo-products: 1. Select photos. 2. Click Order. 3. Select products.Next 24 | Show all 
Enlarge photo 1
1
I had beefed up the floor and ends with some 1 1/2" Box tubing that was 1/8" thick. With the amount of weight I put on it the original sides had given up. I made these so I can slide in extensions when I'm filling my supply for the Winter. For just feeding the stove I leave the extensions off.Main frame was getting springy and the writing was on the wall.

One set of rims were trashed out as the spindles broke from the wheel so some replacements were scrounged. They are now doing the same so some heavier pieces were needed. Getting ready to take off the old gear here.


Enlarge photo 2
2
Had a buddy that was junking out a riding lawnmower and asked if I wanted anything. That's what got the ball rolling for this redo and want to keep the cost low. Different sized tires and it will jack up the deck floor but will save leaning over for me, a plus.

Enlarge photo 3
3
Rear wheels have 2 flats in the hub to make the axles "lock" so the can drive the unit. I just want a simple slip so I'll have to get these round.

Enlarge photo 4
4
Set the wheel assembly up in the drill press and drilled them to size.

Enlarge photo 5
5
We're good to go now and it'll accept a  3/4" shaft.

Enlarge photo 6
6
Up next is the mounts for the wheel assemblies. I want them to be bolt on so I can use them on something else if needed. I used some 1 3/8" box tubing that is 1/8" thick. This design will tie everything up and spread the load. Just winging the locations and build from there. I drill the box tubing on the drill press then clamp it to the frame as shown here. Keeps the holes straight and true that way.

Enlarge photo 7
7
Had a piece of triple wall pipe laying around that will make a nice axle tube. 1/2" wall and just needed a little upsize with a drill. The old lathe took care of that.

Enlarge photo 8
8
For the stands for the axle tube I'm using box tubing. Got the angle needed with a T bevel and transferred  the angle to the chop saw. Made them all the same length.

Enlarge photo 9
9
Here is a trick that makes it easier. Instead of trying to tack the uprights on the frame, do it on the bench. I use the straight edge of the table as a guide and measure the needed spread. A couple of small tacks where they join and they will stand up on their own. here you can see both together and the are the same.

Enlarge photo 10
10
After checking everything I tacked them on, then tacked the centered tube. Rechecked and put a few beads to keep it in place, I'll final weld it all up later.

Enlarge photo 11
11
Here you can see the original small tack weld and once it's all checked, put on a strength weld.

Enlarge photo 12
12
Since there are no bearings, I gun drilled the axle and tapped it for a grease zerk. I crossed drilled a single hole in the middle so the grease can work out from there.

Enlarge photo 13
13
Decided to make some bent straps to add a little strength where the axle tube meets the box tubing. This bender is great for this type of stuff.

Enlarge photo 14
14
Welded on and it's not going anywhere now.

Enlarge photo 15
15
Next is narrowing the front axle. want the tires on the front and back to have the same outside width so 9 inches has to be removed. Chop saw will make this quick and easy.

Enlarge photo 16
16
Cleaned up the cuts and ready to weld back together.

Enlarge photo 17
17
Back as one now and I'll mock it on to see what I need for risers to make it sit level.

Enlarge photo 18
18
This is how I get my measurements. I measure up from the floor on the rear tires and raised the front to the same measurement. Got the distance between the frame and front axle box tube and cut some spacers. Tacked on and checked okay so I'll build from here.

Enlarge photo 19
19
With the axle tacked up, the steering was next. Need a wagon, center style system so I cut the head off a 1/2" bolt. Drove it in about 3/4 of the way and welded it. Then ground flush.

Enlarge photo 20
20
Keeping it centered with the spindles and in the center of the arms is important. This will prevent binding when using. Once checked it was tacked on.

Enlarge photo 21
21
Steering rod was cut to length and ready to weld up. This is the way I do them and not the only way. 2 pieces of steel will keep the straight and I grind the ends like a blunt pencil, then tack.

Enlarge photo 22
22
Grind flush with an angle grinder and rotate. repeat till done all the way around. You'll see why later.

Enlarge photo 23
23
Rod as one again and straight.

Enlarge photo 24
24
I then grind another 1/2" bolts head flush to the body and lay a couple of pieces of steel on both sides. Then clamp with Vise grips and do the aligning. Again, VERY critical to get everything centered and straight so the pivots work in unison.

 Continued ...
 Select All. 
Next 24 | Show all 
 
Album Properties. Email Album. Send Invitation. Share URL